Getting an EV charger approved in a complex or sectional title scheme
You almost certainly cannot just install one. What the body corporate controls, what a trustee can and cannot refuse, and the practical route to a yes.
In a sectional title scheme the parking bay is frequently not yours to modify, the cable run almost always crosses common property, and the electricity supply is often metered to the scheme rather than to your unit. Each of those is a reason the body corporate has a say, and together they are why a charger in a complex is a governance problem before it is an electrical one.
What is actually yours
Under the Sectional Titles Schemes Management Act, a scheme is divided into sections owned by individual owners and common property owned collectively, with parking often held as an exclusive use area rather than as part of your section. An exclusive use area gives you the right to use it, not a free hand to alter it or to run new services to it. Establish which of the three your bay is before you plan anything, because it determines whose permission you need.
- Your section: the unit itself, where you have the widest latitude
- Exclusive use area: yours to use, but alterations and new services need consent
- Common property: collectively owned, and any cable route across it needs approval
The three questions trustees will actually ask
Trustees are rarely opposed in principle. They are worried about specific things, and a proposal that answers them in advance moves considerably faster than one that does not. Who pays for the electricity, and how is it measured. Who is liable if the installation causes a fire or damages common property. And whether the scheme's supply can carry it, particularly if other owners follow.
Capacity is the objection you cannot argue away
A scheme has a notified maximum demand, and chargers are a large, sustained load. One is usually absorbed without difficulty; ten is a supply upgrade. A sensible proposal acknowledges this and suggests a policy for the scheme rather than an exception for you, which is also the argument most likely to win over trustees who expect to face the same request again.
The practical route
- Confirm whether the bay is your section, exclusive use, or common property
- Get a written quote including the cable route across common property and a sub-meter
- Confirm who issues the certificate of compliance and that the scheme receives a copy
- Put it to the trustees as a scheme policy, not a personal exception
- Expect the scheme's insurer to be asked about the installation, and have the certificate ready
Rules and their application vary between schemes, and a managing agent will know the specific scheme's requirements better than any general guide. Treat this as the shape of the process rather than as advice on your particular scheme.
Written and maintained by SunVerified from public sources, each linked below. We publish under the company name rather than invented bylines, and we correct guides when the underlying rules change. Spotted something out of date? Tell us.
Keep reading
PV GreenCard explained: why it matters and how to verify
The PV GreenCard is the single most important credential when choosing an installer. Here's what it is, what it covers, and how to verify one in 30 seconds.
SARS solar tax rebate 2026: what you can still claim
Individuals can no longer claim anything for rooftop solar. Businesses still can, under Section 12B. Here is exactly what is open and what has closed.
Installing a home EV charger in South Africa: what the job actually involves
A wallbox is a fixed electrical installation, not an appliance. What has to be checked, who is allowed to sign it off, and why the cable run matters more than the charger you choose.